Welcome to DU! The truly grassroots left-of-center political community where regular people, not algorithms, drive the discussions and set the standards. Join the community: Create a free account Support DU (and get rid of ads!): Become a Star Member Latest Breaking News General Discussion The DU Lounge All Forums Issue Forums Culture Forums Alliance Forums Region Forums Support Forums Help & Search

TexasTowelie

(112,128 posts)
Fri Sep 9, 2016, 09:44 AM Sep 2016

MOX plant at Savannah River Site will cost $12 billion more than initially thought

AIKEN, SC -- From an upper floor in the federal government’s hulking nuclear fuel plant, construction managers pointed at a section of concrete wall they said was installed incorrectly.

The wall had to be redone so key electrical work could be constructed inside the partially finished building. A few floors down, federal officials nodded at sloping pipes that didn’t meet specifications and unused equipment that had been ordered but never needed.

Those shortcomings are among a multitude of problems that today show how hard it has been to build a mixed oxide fuel factory at the Savannah River Site, according to the U.S. Department of Energy.

The fuel factory, known commonly as the MOX plant, is $12 billion over budget and potentially decades away from completion, according to the latest estimates, released Thursday by DOE officials. Workers began building the plant in 2007.

Read more here: http://www.thestate.com/news/local/article100635952.html

1 replies = new reply since forum marked as read
Highlight: NoneDon't highlight anything 5 newestHighlight 5 most recent replies
MOX plant at Savannah River Site will cost $12 billion more than initially thought (Original Post) TexasTowelie Sep 2016 OP
It seems to be an Obama Adm vs Lindsey Graham-Repub controversy--with Russia also........ riversedge Sep 2016 #1

riversedge

(70,194 posts)
1. It seems to be an Obama Adm vs Lindsey Graham-Repub controversy--with Russia also........
Fri Sep 9, 2016, 09:59 AM
Sep 2016



whow--what a mess!!

.....“The administration’s position .... is that we should move to this alternate method of disposal, which is much, much cheaper,’’ MacWilliams said, noting that the blending process “will result in getting plutonium out of your state decades sooner, and which has really no significant technical risk, unlike the MOX facility.’’

U.S. Sen. Lindsey Graham , a MOX booster, said the alternate plan has not been fully screened and it remains unclear whether all of the plutonium to be neutralized would be suitable for disposal in New Mexico. The South Carolina Republican noted that Russian president Vladimir Putin has voiced concern about not building the plant.

“DOE’s short-sighted efforts to kill MOX have allowed Russian President Putin – who is no friend of the United States and our foreign policy objectives – to claim the high ground,’’ Graham’s office said. “It’s a shame the Obama Administration’s recent words and actions on MOX have unnecessarily harmed our nation’s long-time leadership role when it comes to nuclear nonproliferation.’’.....................

Read more here: http://www.thestate.com/news/local/article100635952.html#storylink=cpy