Welcome to DU! The truly grassroots left-of-center political community where regular people, not algorithms, drive the discussions and set the standards. Join the community: Create a free account Support DU (and get rid of ads!): Become a Star Member Latest Breaking News General Discussion The DU Lounge All Forums Issue Forums Culture Forums Alliance Forums Region Forums Support Forums Help & Search

NNadir

(33,475 posts)
Thu Sep 2, 2021, 10:43 AM Sep 2021

Second Barakah Nuclear Power Plant unit starts up

Second Barakah unit starts up

The Emirates Nuclear Energy Corporation (ENEC) has announced the start-up of the second unit at UAE's Barakah nuclear power plant, thirteen months after Barakah unit 1 reached first criticality. Unit 2's start-up sees Barakah become the first multi-unit nuclear power plant in the region.

The UAE's Federal Authority for Nuclear Regulation (FANR) issued an operating licence for Barakah 2 to its operator, the Nawah Energy Company, in March, with fuel loading beginning soon after. The fuel loading, as well as the comprehensive programme of tests prior to the start-up of the unit, have been carried out under FANR oversight.

ENEC CEO Mohamed Al Hammadi said the startup of Barakah 2 marks a major milestone in the delivery of the UAE Peaceful Nuclear Energy Program. "With the start-up of unit 2, we are now almost halfway to achieving our goal of supplying up to a quarter of our nation's electricity needs and enabling sustainable growth and in parallel, achieving UAE climate change targets," he said.

Preparations will now continue towards grid connection and the start of commercial operations, Nawah CEO Ali Al Hammadi said. "We remain committed to ensuring nuclear operational excellence across all units, and we thank our partners in the UAE and across the globe for their continuous support in helping us achieve these milestones to the highest operating standards," he added.


The bold is mine. Some cultures are more serious than others.

Some additional text:

Four Korean-designed AP-1400 units are being built at Barakah, which is in the Al Dhafra region of Abu Dhabi. The plant is already the largest single source of electricity in the UAE since unit 1, which achieved first criticality in August 2020, entered commercial operation in April of this year. When fully operational, the four unit plant will produce 5.6 gigawatts of electricity while preventing the release of more than 21 million tonnes of carbon emissions every year.

Construction of the first unit at Barakah begin in 2012, with work starting on the other units at roughly yearly intervals: construction of Barakah 2 began in April 2013. Construction of units 3 and 4 is now also in the final stages, with those units respectively 94% and 89% complete as of June this year, according to ENEC.

Nawah is a joint nuclear operations and maintenance subsidiary of ENEC and the Korea Electric Power Corporation.



1 replies = new reply since forum marked as read
Highlight: NoneDon't highlight anything 5 newestHighlight 5 most recent replies
Second Barakah Nuclear Power Plant unit starts up (Original Post) NNadir Sep 2021 OP