HomeLatest ThreadsGreatest ThreadsForums & GroupsMy SubscriptionsMy Posts
DU Home » Latest Threads » TalenaGor » Journal
Page: 1

TalenaGor

Profile Information

Member since: Fri Oct 21, 2016, 05:39 PM
Number of posts: 1,048

About Me

im not new - just reincarnated due to things unrelated to DU -you probably dont know me but if you are concerned, im happy to answer questions

Journal Archives

an engineer on Quora re:the wall

I thought this was absolutely awesome so I wanted to share it with you all....

It outlines the absolute monumental task it would be to build this wall..... I think people sometimes think that you can just throw some cement in the ground lol



Answer to Why are engineers not voicing their opinions on Trump's Border Wall proposal? We are only seeing politicians talking about it. by Kelly Schweighsr

https://www.quora.com/Why-are-engineers-not-voicing-their-opinions-on-Trumps-Border-Wall-proposal-We-are-only-seeing-politicians-talking-about-it/answer/Kelly-Schweighsr?ch=99&share=5cddb408&srid=h825G

You want an engineer’s opinion on “The Wall”? Okay then.

1 - the environmental study will take 3 to 5 years to complete, but only if the project is divided into manageable chunks of 1/2 mile to 2 miles in length. That give us about 1,000 different design sections. And if you think that this phase can be skipped, the lawsuits over that decision will take 10 to 20 years to resolve and the court would probably order the environmental study done anyway.

2 - once you have the environmental clearance, the actual design can begin. Don’t think you need to design something as basic as a wall? The first step is to perform soils testing to see what kind of foundation is needed; skip that and your wall has a good chance of falling down or falling over. While, technically, you could probably design a 1/2 mile section of wall in 3 or 4 working days, you also need to account for the approval process and review times. Chances are that the design stage will take a minimum of 18 months.

3 - acquiring the land/ right-of-way will take from 4 to 6 months, *provided* that the landowner is willing and you don't have to go to court. That gives you time to get an estimate, get the estimate reviewed and approved, contact the land-owner, make the offer, accept a counter-offer (if they make one) and get the documents signed and sealed. If the land-owner does NOT want to sell, expect a protracted court fight of 3 to 7 years (longer if the land-owner has lots of money). If you can't get the land, go back to step 1 and start over.

4 - add on another 4 to 6 months to advertise for bids, accept the bids, make certain that the bidding contractor has done all the proper paperwork and insurance (and isn’t just going to run off with the first payment or produce shoddy work) and generally get the project out the door.

5 - building the stupid thing probably takes the least amount of time, but you will still need to allot 2 months for the contractor to mobilize and order the raw materials, plus another 2 to 6 months for construction.

Now multiply that by 1,000 different sections of wall.

(More at like above)

ty for the heart

my lovely valentine! whoever you are! lol
Go to Page: 1