Welcome to DU! The truly grassroots left-of-center political community where regular people, not algorithms, drive the discussions and set the standards. Join the community: Create a free account Support DU (and get rid of ads!): Become a Star Member Latest Breaking News General Discussion The DU Lounge All Forums Issue Forums Culture Forums Alliance Forums Region Forums Support Forums Help & Search

kristopher

(29,798 posts)
1. Resolve Koodankulam Issues by Dr. A Gopalakrishnan Former IAERB Chair
Fri Apr 26, 2013, 01:36 AM
Apr 2013
"Dr. A Gopalakrishnan, former Chairman of India’s Atomic Energy Regulatory Board, has raised some urgent issues in his article in the New Indian Express that the government must address before commissioning Koodankulam"

Resolve Koodankulam Issues
By Dr. A Gopalakrishnan

24 April, 2013
The Indian Express

The first of the two 1000 MWe VVER nuclear reactors at Koodankulam Project (KKNP-1), under commissioning and testing , is supplied by the Russian atomic energy corporation, Rosatom ,through its subsidiary, Atomstroyexport. On the Indian side , the KKNP project is owned by the Nuclear Power Corporation of India Limited (NPCIL) , a public sector undertaking of the Department of Atomic Energy (DAE) . The overall safety regulation responsibility is with the Atomic Energy Regulatory Board (AERB) .

Crucial materials and reactor parts have been exported to KKNP-1 & 2 by a Russian government-owned company called Machine-Building Plant ZiO-Podolsk (ZiO) , which is another Rosatom subsidiary. ZiO-Podolsk supplies have been sent for years to all the Russian nuclear power plants, and to most of the VVER plants exported to countries like India, Iran, China and Bulgaria. These include important safety subsystems , equipment , components and materials supplied over the years to KKNP-1 & 2 .

KKNP-1 was originally scheduled to start operation in early 2010 , but presently even the final start-up testing is not completed . In January 2013 , the Secretary, DAE, stated that he was totally certain that the reactor would be started that month itself, but it did not happen.

From NPCIL’s continuing inability to start-up KKNP-1 till now , it is very obvious that the Indo-Russian commissioning team at Koodankulam is facing some serious problems which they never anticipated....

Much more at link:
http://www.countercurrents.org/gopalakrishnan240413.htm